The Inputs page allows for
modification of the LMK3H2108 input buffers. Each input consists of the following
fields:
- Input frequency: Used solely
for calculation purposes on the output pages
- Power state: Whether the
input path is enabled or disabled
- Input format: Disabled, INx_P
LVCMOS, INx_N LVCMOS, or INx Differential
- Input termination, capable of
supporting any input format
- Loss of signal behavior
- PCIe Reset (PERST) mode behavior